To be able to create ICEHOTEL and ensuring its construction; provide support to the artists and setting the lights, the construction is done in several phases. As one section is completed, it opens to visitors and overnight guests, while the other sections are still under construction.
The first phase is completed December 10th and each week thereafter a new section opens, until January 7th when the construction of ICEHOTEL is completed. ABSOLUT ICEBAR opens December 12, the Ice Church and the Main Hall are completed December 23.